• User Info
  • Name:
    aman 
  • Submitted By:
     
  • Email:
  • District:
     
  • Town:
     
  • Report Info
  • Report Status:
    Closed 
  • Service:
     
  • System Date:
    16 Jun, 2016 12:52:30 am 
  • Submitted Date:
    15 Jun, 2016 02:45:51 pm 
  • Observation:
    Road is setting Nd damaging due to rain water. There was bridge in British era but now closed by PKHA.. Need to open the bridge now and need to construct side wall. 
  • Priority:
    Normal 
  • Image:

Report Observation(4)

16 June 2016

Submitted Date System Date Observation Submitted By Image Action
15 Jun 2016 02:52:32 pm 16 Jun 2016 12:53:23 am Side wall should need to construct.

16 June 2016

Submitted Date System Date Observation Submitted By Image Action
15 Jun 2016 02:53:23 pm 16 Jun 2016 12:53:24 am under road bridge Nd side wall should be constructed..

30 June 2016

Submitted Date System Date Observation Submitted By Image Action
30 Jun 2016 09:59:32 am 30 Jun 2016 10:11:49 am PKHA has started work on main road to gave way to rain water nd to installed under road pipes, Technical dept has done their job..

30 June 2016

Submitted Date System Date Observation Submitted By Image Action
30 Jun 2016 09:59:32 am 30 Jun 2016 10:12:56 am PKHA has started work on main road to gave way to rain water nd to installed under road pipes, Technical dept has done their job..

Assigned Reports

Assigned Date Due Date Report No. Assigned To Assigned By Internal Note Action

Report Actions

Closing Remarks:

555